Overview

The start curing workflow in QESTField allows for curing information to be added for the specimens created in the field and will be seen when the specimens are received at the laboratory. This workflow can be selected on the Work Order page under the Workflows section when concrete specimens have been added to the work order.

Specimens

The workflow displays curing information about the specimens. Specimens are labelled with their respective Specimen ID, Test Type and Test Date based on the Age of the specimen. The Standard Cure field shows the duration of standard laboratory curing that the specimen(s) will undergo after they have been received in the laboratory prior to testing. The Standard Cure durations are automatically calculated using the Date Received compared to Date Cast.

Field Prompt

Expected Information

Field Prompt

Expected Information

Standard Cure

The duration of standard laboratory curing that the specimen will undergo after being received in the laboratory, prior to testing

The Standard Cure duration is immediately updated after changing the Date Received.

Submitted By

Automatically populated with the user who opened the Start Curing workflow for a concrete sample. This field will be locked once set. 

Condition

Curing condition of the specimen(s). Used for reporting conditions of hardened concrete density tests, if reported. Can be modified later in QESTLab if necessary.

Date Received

Date received in the laboratory for curing.

When the Start Curing workflow is opened, the Date Received is automatically populated.

Time Start Cure

Time the specimen(s) began curing in the laboratory. 

When the Start Curing workflow is opened, the Time Start Cure is automatically populated.

Hours on Site

Time (in hours) the specimen(s) was on site. Calculated from the difference between the Time Moulded on the Concrete Field Data screen and the Time Start Cure from the Start Curing workflow screen. 

Hours on Site is immediately updated when either Date Received or Time Start Cure is modified.

Modifying the Standard Cure Duration

By pressing any specimen's standard cure button, the duration can be modified. If a duration is manually modified it will no longer be calculated automatically. To restore automatic calculation press the  button that appears after pressing the  button. This change is on a per specimen basis.

Non Standard Curing

If the hours on site is not within the standard time, a section is displayed to allow the user to record the reason, and minimum and maximum temperatures for each day. 

 

Field Prompt

Expected Information

Field Prompt

Expected Information

Reason

Reason for non-standard hours on site, populated from the Reason Non Standard list in QESTLab. 

Min./Max. Temperature

Minimum and maximum temperatures for each day the specimen(s) were curing before they were received at the laboratory. These fields will only be shown when the Hours on Site reaches more than 36 hours. 

The number of days shown will depend on the Hours on Site field. 

Shrinkage Specimens (AS 1012.8.4)

The workflow displays curing details for concrete drying shrinkage tests and their specimen sets. Sets are labelled based on the number of specimens present. Information about the curing carried out for the drying shrinkage is recorded here.

Field Prompt

Expected Information

Field Prompt

Expected Information

Externally Prepared

Indicates the specimens were prepared externally.

Use Same Date for All Curing Tasks

For field sampled specimens, checking this checkbox copies the Specimen Receipt Date to the Demould Date and Start Standard Cure Date.

For lab sampled specimens, it copies the Demould Date to the Start Standard Cure Date.

Specimen Receipt Date

This will be initially set to the sample's Date Received.

Specimen Receipt Time

Time the sample was received.

Time On Site

The duration on site.

Demould Date

Locked and copied from the Specimen Receipt Date for field sampled specimens, when Use Same Date for All Tasks is checked.

Demould Time

Time the sample was demoulded

Time in Moulds

The duration from moulding to demoulding.

Start Standard Cure Date

Locked and copied from the Demould Date when Use Same Date for All Curing Tasks is checked.

Start Standard Cure Time

Time the standard curing started.

Initial Curing

The duration from moulding to standard moist curing.

Non-Compliance

This field is enabled when non-standard curing conditions occur.

Reason

The reason why curing was non-standard.

Minimum Temperature

Non-compliance minimum ambient temperature. This field is shown when compliance criteria is not met.

Maximum Temperature

Non-compliance maximum ambient temperature. This field is shown when compliance criteria is not met.

Curing Compliance

Refer to AS 1012.8.4 - Curing Compliance

A warning will also be shown if Initial Curing Conditions are Non-Standard (on the Concrete Field Testing workflow) and Initial Curing is  ≤ 24 hours.





Related content