WA - Soil and Aggregate Field Density Testing Process
QEST Platform 5.0 Documentation
Applies to QESTLab
This article describes the necessary work order structure and data entry process in QESTLab for field density testing to WA test methods.
Contents
Work Order Structure
WA
An example work order structure of a WA density test is shown below.
Work order structure for WA field density tests contain aggregate/soil samples with the following tests as children of the sample:
- Field Density - an option of one of the following:
- Nuclear Field Density
- Field Density Sand Replacement
- Reference Density Result - an option of one of the following:
- Maximum Dry Density - Standard
- Maximum Dry Density - Modified
- Assigned Maximum Dry Density
- Moisture Content
- Dry Density Ratio and Moisture Ratio
And the following tests on the work order level:
- Dry Density Ratio Report
- Lot Conformity (optional)
The worksheets need to be completed so they can be referenced on the Dry Density Ratio and Moisture Ratio worksheet. The exact details for each completing each of these worksheets is explained in the documentation for each specific test method. The results from the Dry Density Ratio and Moisture Ratio worksheet are then reported onto a work order level Dry Density Ratio Report.
Data Entry Process
Kiosk
The discussion below assumes that neither QESTField Tests or QESTLab's Kiosk mode are being used. With QESTField Tests all field results and sample details will be entered by the technician, on site. With kiosk mode, all moisture content results and laboratory test results will be entered using the Kiosk functionality.
- Create a work order and apply the structure discussed above depending on the result of interest.
- Add the number of samples for the work order.
- On the bulk entry screen
- Fill in the sample level information
- The Nuclear Field Density test screen contains all field results hence it can (and should) be filled in immediately after the technician returns from the field
- If oversize is present, enter this information in the "Details" frame on the Dry Density Ratio and Moisture Ratio test screen.
- Enter Moisture Content test data as it becomes available
- Enter the Reference Density data or, if an Assigned MDD is being used, ensure it is up to date
- Back on the bulk entry screen
- The Moisture Content test and Reference Density test data is automatically imported onto the Dry Density Ratio and Moisture Ratio test screen if these tests are on the same sample. If an Assigned MDD is being used, the sample number on which the assigned test resides must be entered. Import the sample level MDD or Assigned MDD result or enter results for an "external" sample.
- Complete the rest of the relevant fields on the "Results" frame Dry Density Ratio and Moisture Ratio test screen.
- Complete steps steps 3 to 5 for other samples included in the field density test on the work order.
- Open the Dry Density Ratio Report to view the report.
Reporting
Results are reported on the following reports.
Dry Density Ratio Report
Properties
QESTID | 18993 |
---|---|
Name | Dry Density Ratio Report |
Child Of | Work Order |
Products described on these pages, including but not limited to QESTLab®, QESTNet, QESTField, QEST Web App, Construction Hive, and associated products are Trademarks (™) of Spectra QEST Australia Pty Ltd and/or related companies.
The content of this page is confidential. Do not share, duplicate or distribute without permission.
© 2021 Spectra QEST® Australia Pty Ltd and/or related companies. Terms of Use and Privacy Statement
Related content
Integrity | Curiosity | Empathy | Unity
The content of this page is confidential and for internal Spectra QEST use only. Do not share, duplicate or distribute without permission.